Introduction
An incredibly bespoke and diverse diesel generator installation project for the WB Team, the specification contained a number of varied infrastructure requirements which WB were required to design and install. The finalised solution comprised one T2200, 2000kVA prime rated generating set installed in an acoustic container, along with an accompanying fuel management solution. The scope also included commissioning, testing and finally, training for the facilities engineering team. The proposed solution also came with a 12 month maintenance package, delivered by the WB Power Service department. This would ensure the generator was kept in full working order.